
Transformer installation and medium-voltage pole removal
Industrial transformer installation, power connections and controlled removal of medium-voltage poles and overhead electrical infrastructure.
- Client
- Coca-Cola FEMSA
- Country
- Guatemala
Modernizing an industrial facility involves more than purchasing new equipment. A successful electrical upgrade must also address transportation, access, positioning, connection and integration with the existing infrastructure.
For this Coca-Cola FEMSA project, STAR completed the installation of an industrial transformer and the controlled removal of poles associated with the medium-voltage network. The intervention brought together electrical work, heavy-equipment lifting, equipment movement and work at height within a single coordinated operation.
One of the main challenges was moving the transformer from the exterior of the facility to its final location inside the electrical room. Because of the equipment's size and the available access conditions, a dedicated maneuver was developed using a crane, slings and tag lines. The crew controlled each movement to maintain load stability and guide the transformer through the opening prepared in the building.
Once inside the facility, the transformer was progressively moved toward the installation area. This stage required constant coordination between the personnel controlling the suspended load and the crew guiding the equipment from inside, preventing contact with the structure and maintaining control throughout the transfer.
After the transformer reached its final position, the electrical work required for its integration into the plant was completed. The scope included conductor preparation, terminal installation and power connections, with an organized layout compatible with the existing switchboards, feeders and cable-management systems.
In parallel, STAR removed poles and components from the overhead medium-voltage infrastructure. These activities were carried out using a crane and aerial access equipment, allowing the structures to be dismantled progressively while keeping elevated components under control.
The project required the coordination of indoor electrical work with outdoor lifting operations, the management of heavy suspended loads and the execution of tasks near energized infrastructure. The result was a comprehensive upgrade that installed the new transformer, reorganized the electrical supply and cleared the areas previously occupied by the former medium-voltage poles.
Technical execution organized by work fronts, with focus on installation, coordination and commissioning.
- 01Planning and coordination of transformer reception, lifting and entry maneuvers
- 02Equipment lifting using a crane and suitable rigging accessories
- 03Suspended-load control using slings, tag lines and specialized personnel
- 04Controlled movement of the transformer into the electrical room
- 05Final positioning of the equipment at its designated location
- 06Preparation, termination and connection of power conductors
- 07Integration of the transformer with existing switchboards and feeders
- 08Organization of conductors and connections inside the electrical room
- 09Disconnection and dismantling of overhead network components
- 10Controlled removal of medium-voltage poles using a crane
- 11Work at height using aerial access equipment
- 12Safety coordination for suspended-load operations
The intervention integrated the transformer into the plant's electrical infrastructure and enabled the controlled removal of medium-voltage poles and components that were no longer required. The coordination of lifting operations, restricted-space movement, power connections and work at height made it possible to complete a complex electrical upgrade safely and efficiently.
Visual evidence
Have a project in mind?
Let's talk about your needs and we will present the most suitable technical solution.



